Part M of Schedule 1 to the Building Regulations 2010 states that a Category 1 “visitable dwelling” should make reasonable provision for people to gain access and use the dwelling and its facilities. More specifically, it requires that visitors can use habitable rooms and a WC within the entrance storey (with step-free access between them) or principal storey if the entrance storey does not contain habitable rooms. Wall-mounted switches and sockets need to be reasonably accessible to people with reduced reach.
On the other hand, optional Category 2 homes are described as “accessible and adaptable dwellings” where, in addition to Category 1 requirements, the provision must be “sufficient to meet the needs of occupants with differing needs, including some older or disabled people” and “to allow adaptation of the dwelling to meet the changing needs of occupants over time.” Here, there should be step-free access to the home, including any associated parking space and private outdoor space connected to the entrance storey.
Critically, a “wide range of people, including older and disabled and some wheelchair users” should be able to use the home and its sanitary features, and features should allow “common adaptations” to be added in future that improve accessibility and functionality of the home.
Category 1 requires principal private entrances (front or rear main access doors) to have a minimum clear opening width of 775mm. With Category 2, this rises to 850mm. Additionally, the step-free principal Category 2 entrance should feature:
There are also more stringent requirements for Category 2 on the approach to the home, which we are not covering here but can be found in Volume 1 of Approved Document M.
The minimum widths of corridors and passageways are the same for both Categories, shown in the table below. The only difference being that Category 2 internal doors on the entrance storey should also have a minimum 300mm nib to the leading edge.
Minimum widths of corridors and passageways for a range of doorway widths | |
---|---|
Doorway clear opening width (mm) | Corridor clear passageway width (mm) |
750 | 900 (when approached head-on) |
750 | 1200 (when approach is not head-on) |
800 | 900 (when approach is not head-on) |
For both Category 1 and Category 2, localised obstructions such as radiators should not be positioned opposite or close to a doorway or at a change of direction, and be no longer than 2m. The corridor width should not be reduced below a minimum of 750mm at any point.
Category 1 is more lenient on step changes within the entrance storey. They should be “avoided where possible” but must comply with the provisions of Part K otherwise.
Category 2 is stricter. Access to all rooms and facilities within the entrance storey must be step-free, and step changes avoided where possible on all other floors. Additionally, the staircase from the entrance storey to the floor above (or below) should have a minimum clear width of 850mm when measured 450mm above the pitch line of the treads, ignoring any newel posts. Stairs must meet the provisions of Part K for private stairs.
Again, there is some commonality between Category 1 and Category 2 for bathrooms, shower rooms and WC/cloakroom facilities. To enable easy access to a WC, both Category 1 and Category 2 require that:
© Crown copyright, 2015. This diagram from Approved Document M is licensed under the Open Government Licence 3.0.
Category 2 provisions further require that:
© Crown copyright, 2015. This diagram from Approved Document M is licensed under the Open Government Licence 3.0.
Category 2 seeks to provide “easy, step-free access between a living area, a WC and the principal private entrance.” Bedrooms also need to offer sufficient access space. Requirements include:
For people with reduced reach, a Category 2 home should ensure all services and controls comply with the following mounting heights:
Item | Height above floor level | Further note |
---|---|---|
Customer unit switches | 1350mm - 1450 mm | |
Switches, sockets, stopcocks, and controls | 450mm - 1200mm | Must be a minimum 300mm (measured horizontally) from an inside corner |
The handle to at least one window in the principal living area | 450mm-1200mm | Unless the window is fitted with a remote opening device within this height range |
Handles to all other windows | 450mm - 1200mm | |
Boiler timer controls and thermostats | 900mm - 1200mm above finished floor level on the boiler | Or separate controllers (wired or wireless) mounted elsewhere in an accessible location with the same height range |
Controls part of a radiator or cooker hood are exempt from these provisions. |
This article provides more information on the provision and positioning of sockets and switches to meet warranty requirements.
Although additional design and build considerations are required to turn a M4(1) Category 1 compliant home to the higher specified, yet optional M4(2) Category 2 standard, many new homes may meet a number of Category 2 requirements by default. With our ageing population and older buyers considering new homes as trouble-free retirement homes, designing and building to Category 2 could make sense to your organisation.
You can download both Approved Document M Volumes 1 and 2 from the LABC website here.