Latest News Blog | Keep up to date with industry news | LABC Warranty

Building regulations and transitional periods

Written by Phil Thomas | Feb 24, 2022 3:50:00 PM

How is “work started” defined?

The Department for Levelling Up, Housing and Communities lists a series of construction details that in its opinion marks the commencement of work. These details were repeated in their circular letter dated December 15 2021.

These details relate to a building control function. From our warranty perspective, additional requirements must be taken into consideration if plots are to be started and left for up to a year.

Please note that there may be restrictions in your terms and conditions that once works have started they need to be completed within 3 years.

The table provides a side-by-side comparison of DLUHC’s definitions and LABC Warranty’s corresponding requirements.

 

DLUHC’s definitions of work commenced Related warranty considerations
Excavation for strip or trench foundations or for pad footings. Strip foundation - the durability and mix of the concrete needs to be suitable for the elements, the whole foundation for the plot must be excavated and concrete laid
Digging out and preparation of ground for raft foundations. Rafts – would need to have frost resistant concrete and increased cover for the reinforcement. Ground reduction and backfill with granular material ready for a raft is a sufficient start.
  Engineered granular fill - seek advice from our engineering department.
Vibrofloatation (stone columns) piling, boring for piles or pile driving. If a site is piled, all the piles to the plot must be installed. Any exposed steel will need to be suitably covered if it is to be left for a length of time. There should be limited site traffic around the area. All piles will still need to be validated in line with our guidance.

Vibrocompaction –
the whole plot/site would need to be completed and left without further excavation. Testing would need to be completed and a survey of “as built” so they are not lost.

If we have contiguous piles for a basement the piles can go in but the basement must not be excavated until continuous work are to happen.
Drainage work specific to the building(s) concerned. Installing drains – not suitable for piled or vibro sites as the foundations must go in first.
DLUHC’s work details not likely to constitute commencement of work Related warranty considerations over details that do not constitute work commencement
Removal of vegetation As stated, plus MMC – an offsite commencement is not a commencement – so even if the modular/panel has been built offsite it is not a commencement.
Demolition of any previous buildings on site
Removal of topsoil
Removal of treatment of contaminated soil
Excavation of trial holes
Dynamic compaction
General site servicing works (eg roadways)